Thursday, April 7, 2011

Our first Inspection

Today the boys finished off the plastic and ties etc ready for our first inspection by the Certifier.  All passed and this means we are ready for the footings pour tomorrow morning.  We are very excited about tomorrow.  There will be a crane used to pour the concrete (with a bucket) from the street.  Once that is the done, the crane will lift the 8 pallets of blocks and place them around for the boys to lay on the footings for the buildup.  Its going to be an amazing site I'm sure.  If we didnt do that, the boys would have to lift and move 700 blocks from the street to the block.  And thats just for the build up.  Pretty amazing.